Friday, December 5, 2014

Construction Coming to an End.

The last few weeks the contractor has been trying to get as much of the project completed as possible prior to the construction season ending. The cold weather we experienced over the past few weeks came a little sooner than expected. Nonetheless, all the work anticipated to be completed was done.

The concrete curb & gutter and first layer of asphalt pavement was completed on Westview Road from the cul-de-sac to Glenarye Drive prior to the Thanksgiving Holiday.

The asphalt pavement surface layer was installed on Central Road, Glendale Drive, and Westview Road. A temporary asphalt surface layer was installed along Glenayre Drive at Glenview. The restoration of asphalt driveways was also completed.

Other work completed through the week included landscape grading and installation of topsoil, pouring benches in manholes, installing chimney seals in manholes, removing debris from catch basins and inlets, adjusting fire hydrant elevations, general site clean-up, and removing equipment from job site. The contractor also installed a strip of erosion control blanket approximately 3 feet wide adjacent to the concrete curb & gutter where the sod will not be installed this year. This is be prevent washout of the topsoil on the roadway. The concrete contractor also applied a protective coating on the concrete curb & gutter, driveways, and sidewalks.

Anticipated work to be completed this construction season includes the following:
·         Internal Televising of storm and sanitary sewers.
·         Re-Install street signs.
·         Pavement markings.
·         Site clean-up. 

Work to be completed in Spring of 2015 (As part of Phase I Improvements):
·         Reconstruction of Glenayre Drive from Glenview Road to Westview Road including concrete curb & gutter, new aggregate base course, asphalt pavement, and landscape restoration
·         Sod restoration not completed this year. 

Phase II Improvement along Glenayre Drive, Glenridge Drive, and Glen Court will be bid during the Spring of 2015 with construction to begin in the spring or summer of 2015.

Thank you again for all your patience and understanding through this construction season. It was greatly appreciated.

Friday, November 21, 2014

First Layer of Asphalt on Westview Scheduled for Saturday, November 22nd

This past week the concrete contractor, Landmark Construction, poured the concrete curb & gutter along Westview Road from the cul-de-sac to Glenayre Drive.

DiMeo Brothers continued with the roadway reconstruction process along Westview Road by grading and preparing the base course for the first layer of asphalt pavement. The contractor also adjusted manholes in the roadway along Glendale Drive to the height of the final asphalt surface elevation. The contractor continued to grade and install soil behind the concrete curb & gutter along Westview Road.

Anticipated work to be completed this construction season includes the following:
·         First layer of asphalt pavement on Westview Road: Saturday, November 22nd
·         Final lift of asphalt pavement surface on the entire project site: Week of December 1st.
·         Grading of landscape areas and installation of topsoil: Weather dependent
·         Installation of asphalt driveways: Week of November 24th or December 1st, weather dependent.
·         Installation of temporary asphalt pavement along Glenayre Drive, Week of December 1st.
·         Miscellaneous repairs and utility work along the project site including manhole adjustments, cleaning of structures, televising of storm sewers, fire hydrant relocations, and others.
·         Site clean-up.

Work to be completed in Spring of 2015 (As part of Phase I Improvements):
·         Reconstruction of Glenayre Drive from Glenview Road to Westview Road including concrete curb & gutter, new aggregate base course, asphalt pavement, and landscape restoration
·         Sod restoration not completed this year. It is unlikely that sod will be available for the remaining of this construction season. The landscape will be graded. Topsoil will be installed if material is available. If topsoil and sod become available due to favorable weather conditions, additional topsoil and sod restoration will be completed. 

Phase II Improvement along Glenayre Drive, Glenridge Drive, and Glen Court will be bid during the Spring of 2015 with construction to begin in the spring or summer of 2015.

Monday, November 17, 2014

Roadway Reconstruction On-Going along Westview Road. Landscape Restoration On-Going.

Following the installation of the concrete curb & gutter the week of November 3rd, the contractor continued with the roadway reconstruction of Glendale Drive from Central Road to Westview Road.

Last week, the first layer of asphalt pavement was installed along the remaining portions of Central Road and Glendale Drive from Central Road to Westview Road.

The contractor also continued with landscape grading, installing topsoil, and laying sod along Central Road and Glendale Drive The contractor will continue with landscape restoration this week with the hopes of having all the sod installed by the end of the week in this area. The sod will be evaluated again in the spring to ensure a healthy stand of grass is established and repair any areas that have settled.

By the end of this week, the contractor is anticipating to have all of the underground utility work completed associated with this project. There are only a few minor items remaining to be completed.

The contractor also started the roadway reconstruction process along Westview Road from the west end towards Glenayre Drive.

This week, the schedule includes concrete curb & gutter being installed along Westview Road on Monday or Tuesday, November 17th or 18th. The contractor will continue with the roadway grading following the concrete curb & gutter installation. The first layer of asphalt pavement is currently scheduled for the end of this week or beginning of the week of November 24th. It is anticipated the first layer of asphalt will be installed along Westview Road prior to the Thanksgiving Holiday.

The current schedule includes installing the final asphalt surface layer on all roadways with concrete curb & gutter that have been previously paved with the first layer of asphalt. This work is scheduled for the first week of December.

As evident by the falling temperatures, the construction season is coming to an end. The contractor is committed to getting as much work completed this year as possible and weather permits. We are still evaluating the extents of the work that will be completed. Whatever roadway reconstruction is not completed this year, a temporary asphalt surface will be installed for easier travel and snow-plowing operations. The roadway improvements will then be completed in 2015 and the temporary asphalt will remain in place until the roadway is reconstructed.

Thank you again for all your patience and understanding throughout the entire construction process, it has been greatly appreciated. We do understand what a huge inconvenience living in and around a construction site can be. We hope you are satisfied with the end result as the asphalt pavement and landscape restoration is being completed.

Friday, November 7, 2014

Work on Saturday November 8th to Begin at 7:00 AM

DiMeo Brothers will be working on Glendale Drive between Central Road and Westview Road starting at 7:00 AM this Saturday, November 8th. The start time is an hour earlier than other Saturday’s due to tight timeframes and change in daylight savings time. The contractor will be performing the landscape grading behind the newly installed curbs and storm sewer improvements on Westview Road.

The asphalt binder pavement along Glendale Drive from Central Road to Westview Road is scheduled to be installed on Tuesday, November 11th.

Thank you for your understanding dealing with this earlier start time.

Sunday, November 2, 2014

Concrete Curb & Gutter This Week

Last week, DiMeo Brothers  continued with the installation of the new storm sewer along Westview Road.
  
This week, the storm sewer crew will continue with the storm sewer installation along Westview Road. It is anticipated the storm sewer work will be completed by the end of the week or early the following week. Once the storm sewer work is completed, all the underground utility improvements will be completed.

Roadway reconstruction of Glendale Drive began last week.  The contractor started approximately 3/4 of the way north of Central Road and worked south towards Central Road. It is anticipated this portion of the roadways will be excavated and new aggregate base installed by the end of the week.

This week, the contractor will return to where they started on Glendale Drive and work north towards Westview Road. The contractor is anticipating to have this portion of the roadway excavated and new aggregate base installed prior to Wednesday.

The major work operation scheduled for this week is the installation of concrete curb & gutter. The concrete curb & gutter will be installed along the remaining portions of Central Road and along Glendale Drive from Central Road to Westview Road. The current schedule is for string-line to be installed on Wednesday, November 5th. Grading of aggregate base and structure adjustments on Thursday. Pour concrete curb & gutter on Friday. We are requesting all residents be out of their driveways by Wednesday, November 5th starting at 7:00 AM to facilitate this construction. Residents will not be allowed back into their driveways for approximately 1 week. We ask that you park your vehicles on the north side of Central Road, south side of Westview Road (west of Glendale Drive only), and west side of Glenayre Drive. Residents will be able to park on the east side of Glendale Drive during the overnight hours, but we ask that all vehicles be moved by 7:00 AM each morning.  We are requesting these parking locations due to the width of the roadways and on-going construction. If you require handicap access please contact Russ Jensen or Chris Baumann so we can make arrangements. 

We understand the significant inconvenience the upcoming work is causing to your daily lives. We thank you in advance for your patience and understanding during this time.

Hope you had a safe and fun Halloween!!!

Sunday, October 26, 2014

Roadway Reconstruction on Glendale Drive to Begin

This past week, DiMeo Brothers  continued with the installation of the new storm sewer along Glendale Drive from Central Road north to Westview Road. The contractor has completed the storm sewer installation along Glendale and will begin working on Westview Road next week.  

Next week, the storm sewer crew will begin at the intersection of Westview Road and Glendale Drive and work west on Westview Road towards the cul-de-sac. The contractor will then begin working east on Westview Road from Glendale Drive towards Glenayre Drive.

Roadway reconstruction of Glendale Drive will begin on Monday, October 27th.  The contractor will start approximately 3/4 of the way north of Central Road and work south towards Central Road. Once this portion is completed, the contractor will return to where they started and work north to Westview Road. Driveway restrictions and partial roadway closures are anticipated during this process during working hours. Residents will be allowed to access their driveways every night. The contractor will notify residents prior to restricting access to their driveways and provide them with the best way to enter and leave the neighborhood.

Concrete curb & gutter along Central Road and Glendale Road is scheduled for November 5th. During this time, driveway access will be restricted for approximately 1 week. Residents will be notified of exact timing and parking options as the construction dates are finalized.

Residents in the neighborhood have been notified via a letter from the Village regarding the upcoming work schedule and will be updated as the work progresses.

Thank you for your patience and understanding as you deal with the construction operations in your neighborhood. The upcoming weeks will be challenging as driveway closures will be wide-spread and effect a significant amount of residents. We thank you in advance for your understanding and patience.

Monday, October 20, 2014

Storm Sewer Continues on Glendale and moving to Westview

Last week, DiMeo Brothers  continued with the installation of the new storm sewer along Glendale Drive from Central Road north to Westview Road. The contractor is currently concentrating on the storm sewer mainline and installation of catch basins and inlets. The contractor has also continued to install storm sewer services along Glendale Drive.

It is anticipated the contractor will complete the storm sewer installation along Glendale Drive this week. The contractor will then begin installation of the storm sewer along Westview Road from Glendale Drive west to the cul-de-sac.

The contractor is anticipating to begin roadway reconstruction on the south end of Glendale Drive at Central Road and working to the north the week of October 27th. This work will consist of excavating the roadway, installing new aggregate base course, concrete curb & gutter, and asphalt pavement. Residents will be notified prior to this work beginning and informed of any potential driveway restrictions.

We would like to express our gratitude to all the residents who live within the neighborhood as they have dealt with the construction operations, especially last week. The rainy conditions posed a huge challenge to the contractor and made the roadways extremely sloppy. Please be assured we are doing everything possible to clean them and provide dry surface to drive on.