Saturday, October 4, 2014

Water Main Installation Completed

This past week, DiMeo Brothers  completed the water service and sanitary sewer service installation along Glendale Drive and Westview Road. The contractor also completed the final connections / disconnections from the existing water main to the new water main. At this point, there does not appear to be any reason for additional scheduled water main shut-downs. The water main improvements are completed.

The landscape contractor also completed the installation and grading of topsoil and installation of sod along Central Road last week.

As the public utility conflicts are now resolved, DiMeo Brothers will begin installation of the storm sewer next week along Glendale Drive starting at Central Road and working north toward Westview Road. During the storm sewer installation, the contractor will be closing the roadway to all traffic during working hours in the vicinity of where they are working for that day. Those residents who live on Glendale Drive, we are asking that you drive around the construction area as much as possible utilizing Glenayre Drive.  When the work is adjacent to your property, access to your driveway will be restricted. The contractor will attempt to notify you prior to restricting access to your driveway to allow you to make arrangement to move cars or park elsewhere.

The Village has made contact with the school districts and bus companies regarding this roadway closure. Thank you for your understanding with the inconvenience this is  causing to your family.