Friday, July 25, 2014

Water Main Under Bike Path Completed.

This past week, DiMeo Brothers completed the water main improvements under the walking / bike path between Chatham Road and Central Road including connecting the new water main to the existing water main.

The contractor also continued to installing the new storm sewer along Central Road between Glendale Drive and Glenayre Drive.

The contractor will be working this Saturday, July 26th, starting at 8:00 AM. Work anticipated to be performed includes pressure testing the new water main under the bike / walking path between Chatham Road and Central Road.

Nicor and NPL were also on-site continuing to replace gas mains and services in the neighborhood.

Next week, the contractor will continue to install storm sewer along Central Road from Glendale Drive moving east towards Glenridge Drive.

Water main testing will also be conducted next week prior to the water main being placed into service.

We apologize for the inconvenience the construction operations have and will cause you.  We thank you and appreciate your patience during the on-going construction.  We would like to especially thank those people that were without water service for a period of time this week while the connections between the new and existing water main were made.

Friday, July 18, 2014

Water Main Installation Between Central and Chatham On-Going

This past week, the gas company continued to install gas mains and services the neighborhood.

DiMeo Brothers started installing the storm sewer improvements at the west end of Central Road.

The contractor also began constructing the new water main along the walking path between Central Road and Chatham Road. Work along this water main section including relocating two water services, abandoning the existing water main, and directional drilling a new water main under the walking path.

Next week, the contractor will complete the water main improvements and connecting the new water main to the existing water main. During the water main connections, there will be disruptions in the water service for some residents along Chatham Road, Central Road, and Glendale Drive. Residents will be notified by the Village of Glenview prior to any water shut-down. Every effort will be made to give 24-hour notice.

The contractor will also continue to install storm sewer next week along Central Road from Glendale Drive moving east towards Glenayre Drive.

We apologize for the inconvenience the construction operations have and will cause you.  We thank you and appreciate your patience during the on-going construction.

Saturday, July 12, 2014

Construction to begin Next Week (July 14th)

This past week, the gas company continued to install gas mains and services in the neighborhood.

DiMeo brothers performed the in-place pavement grinding along Central Road and Glendale Drive. This will allow for a better driving surface and less saw-cutting during the construction process.

Last week, the contractor also began mobilizing equipment and materials.

The contractor will begin installing storm sewer along Central Road at Glendale Drive and move to the east.  This will be the beginning of the major construction work within the neighborhood.

We understand the upcoming construction within your neighborhood will cause a significant amount of inconveniences and delays. Please understand the Village will do everything possible to make the work progress a smoothly as possible.

Thursday, July 3, 2014

Gas Main and Service Replacement On-Going

This past week, the gas company continued to install gas mains and services along Central Road and mainlines along Glendale.

Due to the slower completion of the gas main and service replacements on Central Road, the contractor for the Village improvements has been delayed in starting the work.

The current schedule has the contractor beginning to mobilize late next week. The existing asphalt pavement will then be ground up and left in place prior to the storm sewer work beginning along Central Road.  At this time, we anticipated the storm sewer work along Central Road to begin the week of July 14th.

Have a Happy and Safe 4th of July Holiday.