Water Main Installation Between Central and Chatham On-Going

This past week, the gas company continued to install gas mains and services the neighborhood.

DiMeo Brothers started installing the storm sewer improvements at the west end of Central Road.

The contractor also began constructing the new water main along the walking path between Central Road and Chatham Road. Work along this water main section including relocating two water services, abandoning the existing water main, and directional drilling a new water main under the walking path.

Next week, the contractor will complete the water main improvements and connecting the new water main to the existing water main. During the water main connections, there will be disruptions in the water service for some residents along Chatham Road, Central Road, and Glendale Drive. Residents will be notified by the Village of Glenview prior to any water shut-down. Every effort will be made to give 24-hour notice.

The contractor will also continue to install storm sewer next week along Central Road from Glendale Drive moving east towards Glenayre Drive.

We apologize for the inconvenience the construction operations have and will cause you.  We thank you and appreciate your patience during the on-going construction.