Sunday, October 26, 2014

Roadway Reconstruction on Glendale Drive to Begin

This past week, DiMeo Brothers  continued with the installation of the new storm sewer along Glendale Drive from Central Road north to Westview Road. The contractor has completed the storm sewer installation along Glendale and will begin working on Westview Road next week.  

Next week, the storm sewer crew will begin at the intersection of Westview Road and Glendale Drive and work west on Westview Road towards the cul-de-sac. The contractor will then begin working east on Westview Road from Glendale Drive towards Glenayre Drive.

Roadway reconstruction of Glendale Drive will begin on Monday, October 27th.  The contractor will start approximately 3/4 of the way north of Central Road and work south towards Central Road. Once this portion is completed, the contractor will return to where they started and work north to Westview Road. Driveway restrictions and partial roadway closures are anticipated during this process during working hours. Residents will be allowed to access their driveways every night. The contractor will notify residents prior to restricting access to their driveways and provide them with the best way to enter and leave the neighborhood.

Concrete curb & gutter along Central Road and Glendale Road is scheduled for November 5th. During this time, driveway access will be restricted for approximately 1 week. Residents will be notified of exact timing and parking options as the construction dates are finalized.

Residents in the neighborhood have been notified via a letter from the Village regarding the upcoming work schedule and will be updated as the work progresses.

Thank you for your patience and understanding as you deal with the construction operations in your neighborhood. The upcoming weeks will be challenging as driveway closures will be wide-spread and effect a significant amount of residents. We thank you in advance for your understanding and patience.

Monday, October 20, 2014

Storm Sewer Continues on Glendale and moving to Westview

Last week, DiMeo Brothers  continued with the installation of the new storm sewer along Glendale Drive from Central Road north to Westview Road. The contractor is currently concentrating on the storm sewer mainline and installation of catch basins and inlets. The contractor has also continued to install storm sewer services along Glendale Drive.

It is anticipated the contractor will complete the storm sewer installation along Glendale Drive this week. The contractor will then begin installation of the storm sewer along Westview Road from Glendale Drive west to the cul-de-sac.

The contractor is anticipating to begin roadway reconstruction on the south end of Glendale Drive at Central Road and working to the north the week of October 27th. This work will consist of excavating the roadway, installing new aggregate base course, concrete curb & gutter, and asphalt pavement. Residents will be notified prior to this work beginning and informed of any potential driveway restrictions.

We would like to express our gratitude to all the residents who live within the neighborhood as they have dealt with the construction operations, especially last week. The rainy conditions posed a huge challenge to the contractor and made the roadways extremely sloppy. Please be assured we are doing everything possible to clean them and provide dry surface to drive on.

Friday, October 10, 2014

Storm Sewer Continues on Glendale Drive

This past week, DiMeo Brothers  started installation of the new storm sewer along Glendale Drive from Central Road north to Westview Road. The contractor is currently concentrating on the storm sewer mainline and installation of catch basins and inlets. It is anticipated the storm sewer service installations will begin later this week and continue next week.

Next week the contractor will continue to install the mainline storm sewer along Glenedale Drive towards Westview Road.

Once the contractor gets to Westview Drive, they will begin the roadway reconstruction process on the south side of Glendale Drive at Central Road and work north behind the storm sewer installation crew.

We would like to thank you for your understanding and cooperation in utilizing Glenayre Drive in lieu of Glendale Drive during the storm sewer installation.

Saturday, October 4, 2014

Water Main Installation Completed

This past week, DiMeo Brothers  completed the water service and sanitary sewer service installation along Glendale Drive and Westview Road. The contractor also completed the final connections / disconnections from the existing water main to the new water main. At this point, there does not appear to be any reason for additional scheduled water main shut-downs. The water main improvements are completed.

The landscape contractor also completed the installation and grading of topsoil and installation of sod along Central Road last week.

As the public utility conflicts are now resolved, DiMeo Brothers will begin installation of the storm sewer next week along Glendale Drive starting at Central Road and working north toward Westview Road. During the storm sewer installation, the contractor will be closing the roadway to all traffic during working hours in the vicinity of where they are working for that day. Those residents who live on Glendale Drive, we are asking that you drive around the construction area as much as possible utilizing Glenayre Drive.  When the work is adjacent to your property, access to your driveway will be restricted. The contractor will attempt to notify you prior to restricting access to your driveway to allow you to make arrangement to move cars or park elsewhere.

The Village has made contact with the school districts and bus companies regarding this roadway closure. Thank you for your understanding with the inconvenience this is  causing to your family.