DiMeo brothers performed the in-place pavement grinding
along Central Road and Glendale Drive. This will allow for a better driving
surface and less saw-cutting during the construction process.
Last week, the contractor also began mobilizing equipment
and materials.
The contractor will begin installing storm sewer along
Central Road at Glendale Drive and move to the east. This will be the
beginning of the major construction work within the neighborhood.
We understand the upcoming construction within your
neighborhood will cause a significant amount of inconveniences and delays.
Please understand the Village will do everything possible to make the work
progress a smoothly as possible.