Due to the slower completion of the gas main and service
replacements on Central Road, the contractor for the Village improvements has
been delayed in starting the work.
The current schedule has the contractor beginning to
mobilize late next week. The existing asphalt pavement will then be ground up
and left in place prior to the storm sewer work beginning along Central Road. At
this time, we anticipated the storm sewer work along Central Road to begin the
week of July 14th.