The major item of construction last week was the
installation of the first two layers of asphalt pavement along Central Road from
Glenridge Drive to Glendale Drive. The third, and final, surface layer of
asphalt pavement will be installed later in the year once the construction
along the other roadways in completed.
This week, the contractor will continue to install water
services and sanitary sewer services to each resident along Glendale Drive.
New water services will be installed from the new water main
to the existing b-box within the Village right-of-way. New services will not
be installed all the way to your home. During water service installation, water
to individual homes will be turned off while the transition is made. Typically
the water is turned off for 1-hour. The contractor will knock on the door of
each home prior to turning off the water. It is difficult to determine the
exact timing of the water shut-off; therefore, 24-hour notice is not given. The
contractor will work with you to determine the best time to shut-off the water
to the greatest extent possible.