Tuesday, August 19, 2014

August 18, 2014

The general contractor DiMeo Brothers, Inc. started the water main installation on Glendale Drive late last week and is anticipating continuing the water main installation on Westview before the end of this week.  In preparation for this underground work on Westview Road, on Tuesday 8-19-14 the road will be ground up into a crushed asphalt base which will allow for vehicle access to all driveways, reduce pavement saw-cutting and provide the maximum flexibility for water main underground construction.