Water Main Installation along Glendale Drive Started

This past week, DiMeo Brothers completed the new storm sewer along Central Road between Glendale Drive and Glenridge Drive. The contractor also started the new water main installing along Glendale Drive starting at Central Road and moving north towards Westview Road.  During the water main installation, there will be some scheduled water main shut downs. Residents will be notified prior to any scheduled disruption in water service.

As always with underground utility construction, the potential of water main breaks is always present. Should this occur, the water main will need to turned off to repair the damage. Every effort will be made to notify those effected residents as soon as possible.

Next week, the contractor will continue to install water main along Glendale Drive from Central Road up to Westview Road. The contractor will also install the storm sewer services to those homes adjacent to the Central Road storm sewer.

Once the storm sewer services and remaining underground utility work is completed along Central Road, the contractor will begin roadway reconstruction in this area. The roadway reconstruction will include removing the existing asphalt pavement and soils below the pavement, installing an aggregate base course, concrete curb & gutter, and asphalt pavement. The process will take a few weeks to complete, but could begin near the end of next week. Residents will be notified of any access restrictions to their driveways during the roadway reconstruction process.

Thank you again for your understanding and patience as you deal with living within a construction area. The Village is committed to doing everything possible to minimize the inconveniences associated with construction.