Friday, August 22, 2014

Water Main Installation On-Going

This past week, DiMeo Brothers continued with the water main installation along Glendale Drive between Central Road and Westview Road.  

Next week, the contractor will continue to install the new water main along Westview Road. The contractor is anticipating to start along Westview Road working west towards the cul-de-sac. Once that section is completed, the contractor will work east of Glendale Drive towards Glenayre Drive and Glenview Road.

The contractor is also anticipating to complete the storm sewer services along Central Road next week.

Roadway reconstruction including removing the existing soils under the roadway, installing new aggregate base, concrete curb & gutter, and asphalt pavement will begin following the Labor Day weekend. The entire roadways reconstruction process will likely take 2 to 3 weeks along Central Road. Residents will be notified of any restrictions to their driveways prior to the work beginning.